Here the typical works of a civil engineer(Real estate project) is mentioned
The works can be divided into the following six categories:
• STRUCTURE
• COMMON AREA
• TERRACE
• LIFT
• BASEMENT
• EXTERNAL
Structure (start to finish)
It includes everything like foundation,beam,column, masonry works,electrical,plumbing,painting and tiling works.
- The site boundary and marking pillars are marked and is cross checked with reference to the setting out drawing
- Receipt of approved current construction drawing for footing and excavation (Architectural & Structural) from Architects.
- Checklists for all the activities to be filled and approval taken.
- Mass excavation /manual excavation are started.
- Anti termite treatment is done.
- PCC for footing with soling (if required) to be done.
- Marking for footing and columns.
- Reinforcement for footing.
- Shuttering/form work for footing.
- Concreting for footing.
- Pedestal marking and concreting.
- Column marking / casting
- Reinforcement/lapping.
- Column box shuttering,
- Column concreting
- Meter marking/staircase columns.
- Beam bottom marking/shuttering.
- Shuttering for beam side / slab.
- Leveling and QC/ Architects checking.
- Reinforcement for beam, beam bottom, electrical conduiting, plumbing cutout and top mat.
- Beam outer side shuttering.
- Check by structural consultant /QC.
- Pour card/batch ticket signature to be taken.
- Concreting of slab/beam supervised under the PH (Staircase and Lift wall are cast along with the structure).
- Cubes are cast as per Indian Standards.
- Sprinkling of water to be started the moment concrete surface starts to dry.
- Ponding / hessain cloth curing to be done for 7 days
- Column starter marking for the next floor.
a. Repeat the procedure from point 12-27 for the next level.
- De-shuttering started after achieving required strength as per IS requirements. (With temporary supports to beams/slabs).
- Hacking to be done on concrete surfaces for plastering and slurry coat to be applied to concrete surface at junction of block workand concrete.
- Marking course of block work is done and is checked by Quality Engineer.
- Block work done using templates for doors and windows openings.
- Meter marking is done on the block work with coloured line dori
- Lintels/sills/chejjas are cast with reference to meter level.
- Mesh fixing is done at the junction of block work and concrete and is packed with mortar.
- Ceiling plastering is done. (PVC rings are provided for the electrical junction boxes).
- Button marking for the wall plaster is done.
- Electrical chasing, conduiting and box fixing including DB box fixing and packing are done.
- Window grills and balcony railings are fixed.
- Wall plastering is completed including the toilets. Meter marking is again done on the surface as explained earlier.
- Plumbing chasing, pipe fixing in toilets/kitchen is completed and tested and packing is done
- Electrical wiring is completed.
- Fire sprinkler works are completed.
- Main floor screed for tilling is completed.
- Bore packing in toilets, balconies and utilities are completed.
- Ponding test is done to check the water tightness of the bore.
- Screeding for toilets, balconies and utilities are done.
- Internal painting comprising of primer, 2 coats of putty for ceiling and wall is done.
- Toilet and kitchen dadoing is completed. ( except for bottom line of tile)
- The main flooring is completed and the tile surface is protected.
- Under tile waterproofing is done for toilets, balconies and utilities.
- Floor tilling for toilets and balconies are completed and protected.
- Skirting for the main flooring is completed and the last tile dadoing is finished.
- Window sill and balcony coping granite works are completed.
- Sanding and first coat paint to ceiling and wall is completed.
- False ceiling frame works and E-board works in balconies and utilities are completed.
- Texture and first coat paint for balconies and utilities are done.
- Aluminum windows, ventilators and doors are fixed.
- SIL door frames and shutters are fixed.
- Electrical switch plates are fixed.
- Touch up putty and sanding to wall and ceiling are done.
- False ceiling works in toilets are completed.
- Grouting of wall and floor.
- Final coat paint.
- Plumbing fixtures are fixed.
- Silicon sealant works are completed for toilet and kitchen areas.
- Final snagging and handover of flat to CRM.(Refer Clearance Process from QST)
Common Area Works
- Staircase and Lift wall to be constructed along with structure.
- Block work for common area and shafts are completed.
- Electrical conduiting and box fixing is completed.
- Staircase wall and ceiling plastering is completed.
- Lobby area plastering is done.
- Staircase railing and lobby railings are fixed.
- Staircase and common area flooring and dadoing (as per specification) are completed.
- Granite coping and lift architraves granite works are completed.
- Putty, sanding and first coat paint to ceiling are completed.
- Services like Plumbing and fire are completed.
- Electrical wiring works are completed.
- Shaft door fixing is completed.
- Shaft door painting is completed.
- Grouting of floor tile, wall tile and granite are done.
- Silicon sealant works are completed.
- Signages are fixed.
- Final snagging and handover of common area to CRM.
Terrace Works
- Up stand beam to be cast by providing provision for stub columns.
- Concreting of stub columns.
- Parapet block work completed.
- Coping for the parapet wall done.
- Structural works such as OHT, Staircase headroom, Lift machine room, flush tank, battery room etc. to be completed.
- Block work to be completed for all the above mentioned service rooms.
- Electrical conduiting & Box fixing works to be completed.
- Ponding test to be done to check the water tightness of the terrace slab.
- Tanks to be filled with water and water tightness to be checked.
- Kurrah fixing (Outlet for draining rain water) to be completed with bore packing.
- Bull strips are made.
- Light weight screed is completed to slope.
- Haunching to be done at the junction of all vertical and horizontal surfaces to enable smooth transition of waterproofing.
- Waterproofing as per waterproofing calendar /Specifications issued to site.
- Protective screed for the waterproofing done.
- Plastering for all surfaces to be completed.
- Plumbing bracket fixing work to be completed.
- Terrace pipe line works to be completed.
- Terrace flooring works to be completed.
- Skirting works to be completed.
- Miscellaneous works such as OHT ladder fixing, staircase handrail for lift machine room, door fixing for the rooms, painting works, fixing of solar panels & water heaters, lightning arrester, aviation lights etc. to be complete
- External painting to be completed.
- Painting for all the MS works.
- Expansion joint treatment to be completed (if any).
- Non-shrink expansion joint material to be filled as the specification.
- Snagging and hand over to CRM.
Lift Works
- Lift well waterproofing is completed.
- Lift wall to be constructed along with structure.
- Block work for the lift openings to be done as per manufacturer’s drawing.
- Lintel to be cast with allowance for granite architrave.
- Lift well block work plastering to be completed.
- White washing to be done to the lift well.
- Electrical conduiting is done; bulk heads and socket points are fixed.
- Lift frame and door is fixed by vendor.
- Granite frame and architrave are fixed.
- After handover of lift from the agency, the lift flooring to be done.
- Protection done for the walls and the ceiling of lift.
- Final snagging and handover of Lift to CRM
Basement Works
- Backfilling to be done in layers and compacted.
- Soil profile to be graded as per the required slopes.
- Anti-termite treatment to the soil is done.
- Car wash drains and tanks to be constructed.
- Soling is done to the required profile.
- PCC is done.
- All the high level services such as electrical, plumbing, fire are completed.
- Lift lobby works are completed.
- The services rooms such as panel rooms, telecom rooms, pump rooms, Water treatment plants, maintenance room etc… are completed.
- VDF (Vacuum dewatered flooring) is completed.
- Car wash drain covers are placed.
- Ceiling painting (Tyrolene) to be completed.
- Column and wall painting to be done.
- Electrical light fittings and car wash lines are completed.
- Car park numbering and marking to be completed.
- The shaft openings are enclosed in the basement.
- Column fenders are fixed.
- Signages and letter boxes are to be fixed.
- Final snagging and handover of basement to CRM
External Works
- Retaining wall waterproofing and back filling to be done.
- Anti termite treatment to be done to the areas surrounding the building.
- Underground services such as Plumbing, Fire, Electrical works to be completed.
- DG yard, transformer yard, STP, UG sump, Organic waste converter, security cabin, gate etc… to be completed.
- Shafts block work, plastering, plumbing lines, shaft door fixing etc...to be completed.
- External plastering and external painting to the building is completed.
- Podium waterproofing to be completed.
- Podium hard landscaping to be completed.
- Storm water drainage to be completed.
- Compound wall works to be completed.
- Driveway soling, PCC, kerb stones and pavers completed.
- Bore well connections, rain water harvesting pits etc... to be completed.
- Swimming pool, clubhouse and other external facilities as per drawings are to be completed.
- Soft landscaping to be completed.
- Electrical lighting to be completed.
- Snagging and handover to CRM.